Energy & Critical-Maintenance Crane Systems

Lift out the component.
Make room for the repair.

Cranes for turbine and generator installation, hydropower equipment and planned plant maintenance. Start with the component to remove, the lifting path and where it will be set down.

Double-girder crane with an open trolley, access platforms and suspended hook in an industrial hall
Power-station crane · equipment exampleLifting, positioning and access around major plant equipment.

01 · Choose the equipment

Inside the powerhouse.
Or above the gate.

The load, travel path and operating environment lead to different crane arrangements. Select a group to see the information that changes the design.

Power-station crane example with large reeved lifting block, smaller auxiliary hoist and access stairs

01 · Turbines · generators · major plant equipment

Powerhouse bridge cranes

Lift and position components between the installed machine, the loading bay and a maintenance area. Main and auxiliary lifting arrangements can serve different loads.

Check suitability
Turbine and generator work
Identify the rotor, casing or other component to remove, its lifting points and the headroom needed with the rigging attached. Review the complete removal and return path.
Hydropower unit maintenance
Include vertical withdrawal from the unit pit and transfer to the assembly floor. Confirm the component dimensions, hook travel and available landing space.
Auxiliary equipment
Pumps, valves and smaller assemblies may be better served by a dedicated hoist, monorail or jib. Check whether the main crane can reach and whether it must remain available for another lift.
Outdoor dam gantry crane with tall portal legs, an auxiliary boom and rail-mounted travelling assemblies

02 · Intakes · outlets · gates and stoplogs

Hydropower gate cranes

Use a mobile gantry or a dedicated hoisting arrangement to serve defined gate slots and handling areas. Gate operation and removal for maintenance need separate review.

Check suitability
Match the gate interface
Provide gate and stoplog drawings, lifting-point spacing and the lifting-beam or grabbing-beam interface. Define how engagement is checked.
Define the lifting conditions
Gate weight alone is not the required hoisting force. Specify the water conditions, friction and the intended operating or maintenance duty with the gate designer.
Review the exposed location
Confirm rail arrangement, hook travel, wind exposure, corrosion conditions, parking restraints and access. The pictured auxiliary boom is an example, not a standard inclusion.

02 · Inside the crane

Different lifts.
Different provisions.

Select a numbered area. This equipment example shows separate lifting arrangements and access; the required capacities and controls depend on the lift plan.

Power-station crane example with large reeved lifting block, smaller auxiliary hoist and access stairs
Equipment example · no model ratings implied

03 · Outage planning

Design for the actual lift.
Prepare before the shutdown.

A crane may stand idle for months and then work intensively during an outage. Include slow-running time, repeated positioning and readiness after storage in the review.

From installed position to landing areaUse the plant layout and component lifting drawings for these checks.
Load and lifting pointsInclude the component and rigging weight, centre of gravity and approved lifting points. Any coordinated lift needs a specific load-sharing and control plan.
Removal path and landing areaCheck withdrawal height, hook approaches, obstructions and the space needed to set down and work on the component.
Duty during the outageReview time spent positioning at low speed, starts and load combinations. Few operating days do not automatically mean a light-duty design.
Readiness and recoveryPlan inspection after idle periods, access to service items and the agreed response to interrupted movement or power loss.
01What belongs in the supply scope?

Agree the crane or hoisting equipment, lifting attachments, controls, runway or rail interfaces and documentation. Identify responsibility for structural verification, installation, testing and commissioning, including temporary works and access required at the plant.

02What should be verified before the outage?

Agree the inspection and test programme for the selected equipment and site. Check the required lifting movements, limits and protective functions, and demonstrate relevant interfaces and recovery arrangements. Confirm that the component can reach its landing area with the intended rigging.

04 · Project questions

New installation?
Or an existing plant?

The initial review should identify what can be retained and what the next lift will demand.

01Can the existing crane be upgraded for the next overhaul?

Start with its nameplate, drawings, condition and the proposed load and lifting sequence. Controls or drive upgrades may improve handling, but they do not by themselves increase the crane rating or make the supporting structure suitable for a heavier lift.

02Do two hoists or two brakes make a crane redundant?

Not by themselves. Multiple lifting points, additional braking and independent load paths solve different problems. Define the failure conditions, load retention and recovery required, then review the complete arrangement.

03Can the same crane cover erection and later maintenance?

Often it can, but both tasks must be included from the start. Erection loads, building access, later component-removal routes and auxiliary lifting needs may differ. Do not assume the first installation lift covers the future maintenance requirement.

Existing equipment

Need a controls upgrade?

Explore positioning assistance, controls renewal and automation for retained equipment.

View Automation

05 · Start the discussion

Show the component.
Mark its removal path.

Send the drawings and photos you already have. The first review can identify a suitable equipment arrangement and the inputs needed for a proposal.

Discuss an energy lift
  1. The equipmentComponent or gate drawings, weight and lifting points; existing crane details if applicable
  2. The sitePlant layout, lifting and landing positions, available headroom, rails or runway, and access photos
  3. The programmeErection or outage dates, expected lift sequence, slow-positioning needs and scope of site work